Failure to comply with the deadline set for the conclusion of the final contract and containment measures by Covid-19
- 28/07/2020
With a decree of 8 July 2020, the Court of Verona rejected an appeal for an injunction with which it was requested to order the payment of the amount - corresponding to the agency costs and double the deposit - allegedly due to the recurring as a result of the failure by the promissory seller of the obligation to enter into a definitive property purchase contract. The Court of Verona has established that compliance with the prohibition of transfer outside the region established by the Decree of the President of the Council of Ministers of 17 May 2020, as a cause of the failure of the promising seller to appear before the notary for the stipulation of a real estate sale, exempts the liable for default liability.
NEWS
The Council of State reaffirms some principles in the field of public procurement
02/05/2024The Council of State, Section V, in its judgment of 12 February 2024, no. 1372, rendered on the subject of tender contracts, ruled that the instrument of "soccorso istruttorio" cannot be used to re...
The Contracting Authority enjoys wide discretion in the evaluation of technical offers
18/04/2024The Council of State, section V, in its judgement of 27 February 2024, no. 1911, rendered on the subject of tenders, reaffirmed that "the evaluation of the tenders and, likewise, the awarding of sc...
- 15/04/2024
The Court of Cassation, in its judgement of 20 March 2024, no. 7329, rendered in banking matters, ruled that "in bank account agreements, the statement of account balance has evidentiary effectiven...